Design-Build
Delivery Method Comparison
Adjusted Score DB
1 yr
2 yr
3 yr
RFP Development
6-12 mos.
2-3 mos.
RFP LOI
MultipleTeamsShortlisted
1-2
6-9 mos.
ATC Process / Potential RFP Addendums
3-4 mos.
Tech Proposal + BidPrice / Selection *
36-72 mos.
Design and Construction
Phased DB
RFQDev.
1 mo.
RFQLOR
1-2
Single Team Selected *
1-2
Planning / Innovation Phase (30% Design) / 30% OPCC
6-9 mos.
Design and Construction
36-72 mos.
Modified Phased DB
RFQDev.
RFQLOR
MultipleTeams Selected *
Design and Construction
1 mo.
1-2
1-2
4-6 mos.
36-72 mos.
Clickfor More!
Contracted Team 1Prepares Innovations
Contracted Team 2Prepares Innovations
Teams incorporate Approved Innovations and Scope Enhancements into their respective concepts.
Contracted Team 2Submits RtC(s) per submission schedule.
Contracted Team 3Submits RtC(s) per submission schedule.
Contracted Team 1Submits RtC(s) per submission schedule.
Work Orders Issued to Contracted Team X based on best value RtC submission.
Requires Fully Committed and Immersed Delivery and Oversight Teams
NOTE: Durations shown for each delivery method are for comparison purposes only and will fluctuate on a project-by-project basis.
* Contract(s) executed.
AcceleratedInnovation and
Collaboration Phase
Accelerated Innovation and Collaboration Phase
Contracted Team 1Planning / Innovation Phase
Contracted Team 2Planning / Innovation Phase
Contracted Team 3Planning / Innovation Phase
Department DeterminesInnovations and Sets Scope
Contracted Team 1GMP + Time Submission
Contracted Team 2GMP + Time Submission
Contracted Team 3GMP + Time Submission
Work Orders Issued Basedon Weighted GMP and/orTime Calculation to Contracted Team X
Accelerated Innovation and Collaboration Phase
Contracted Teams:
Each team establishes independent risk registers, which the Department reviews. Department sets and notifies teams of the overall risk value and categories (same for all teams). Teams price job accordingly based on assigned risk pool value.
Department reviews confidential team innovations for approval, sets value-added scope enhancements, and evaluates risk elements.
Contracted Team 3Prepares Innovations